Developments, Industrial, Retail & Leisure

VALUE: £tbc

Duration: Phased developement

Barnfield Construction is onsite developing the 90 acre Frontier Park situated just off Whitebirk Roundabout on the border of Hyndburn/Blackburn.

Frontier Park is a new mixed-use development with planning consent for circa 1 million sqft. of industrial and warehouse accommodation, which has immediate access to J6, M65.

Currently under construction at the park are:

  • Infrastructure works – prepare the ground for each plot and create roads –  COMPLETE
  • Euro Garages service area incorporating BP petrol filling station, Starbucks, KFC, Subway and Greggs – COMPLETE
  • FP One – a 185,500 sq ft detached self-contained distribution / industrial unit, with separate HGV and car access.  The unit is built to institutional standards incorporating 18 loading doors, 53m deep service yard and 12.5m clear height to the underside of haunch – COMPLETE – http://frontierpark.com/fp-one/
  • Pioneer Court
    Phase 1 of industrial / manufacturing units 135,000 sqft which will be future proofed to provide options for end users – COMPLETE
    Phase 2 incorporates units 2, 3 and 4 totalling 80,000 sq ft – COMPLETE – http://frontierpark.com/pioneer-court/
  • Hampton by Hilton – A 112 bedroom hotel – COMPLETE
  • Plot C – A speculative development of 276,000 sqft. of industrial space.  The plot will comprise 2 buildings – Unit A/B £150,000 sqft. and Unit C/D 126,000 sqft. – COMPLETION SPRING 2021

Check in on progress at the Barnfield Construction YouTube channel – here

Read about the sod cutting – here

Enquire about space on the park  – here